Thursday, 26 April 2012

Upper Level Acid Wash

We had our upper level bricks washed this morning. They have come up pretty well.

This picture shows just how well they have come up - top is cleaned, bottom is not

Wednesday, 25 April 2012

Roof and Eaves

A few shots of the roof, guttering, eaves, and fascia.

Paperbark eaves and fascia, with monument gutters, and barramundi roof tiles (unseen)

Just cannot see tiles from this position

A shot of our "pergola" over our balcony... will look much nicer once painted.

Front left of house looking towards front door.

Friday, 20 April 2012

Roof finished (Upper)

Our upper roof was completed today. It took one day to get the beams and sarking installed and a further day to lay all the tiles. The lower roof (garage and rear of house) will be completed once the scaffolding is removed. No pictures, as I can barely see the roof from the road. Will need to get my zoom lens out and take a shot from distance :)

Tuesday, 17 April 2012

Guttering and Fascia

The top floor guttering and fascia were installed today - just as the rain started to fall.

Monday, 16 April 2012

Brickwork Completed


Bricks are now (semi) completed. There are a few chipped bricks that need to be replaced and I'm sure we'll find even more, once the bricks are cleaned. Really hanging out for the cleaning now :)

The guttering and fascia have also been delivered and should be started tomorrow. 

Monday, 2 April 2012

Scaffolding


On the weekend we saw that the bricks have now been moved upstairs and it looks like today was spent installing the scaffolding. Tomorrow should be the start of the upstairs brickwork.