Tuesday, 22 May 2012

Lower Bricks Cleaned

Came past tonight to see that all the lower bricks have been cleaned.

Looks like EBH will have to do a lot of touch ups. There is quite a lot of mortar that has come out and way too many chips on the bricks.

Wednesday, 16 May 2012

Lower eaves and cladding


Garage eaves - really hanging to see the brickwork cleaned and the eaves painted :)


The only cladding we have on the house is at the rear - which is fantastic for us as we really aren't excited to have any cladding, but it looks fine anyway.

They have also installed all the cavity door frames and nailed the frame and bricks together. Air conditioning and electrical rough in were completely finished today also.

Tuesday, 15 May 2012

Lower roof finished


Due to a disappearing act from the roofers on Thursday and Friday, the roof did not get completed until this morning.



Electricians onsite yesterday and today and the ducting was delivered this morning so this should be installed today too.

This morning the brickies were also back onsite replacing some chipped or cracked bricks, including the wall above the alfresco that was leaning over. WIll give this the once over this afternoon.

Thursday, 10 May 2012

Lower roof guttering and fascia

Over the last 2 days the lower roof has been worked on. Hopefully when we go past this afternoon, the roof tiles will be completed.

Hoping to get there earlier enough to see the house in the daylight for some pictures.