Tuesday, 10 July 2012

Slow week

It's been a week since my last post and that's because very little has been happening.

Received our update from the SS last week and he advised that the following will happen in the next 2 weeks:

 - painting completed
 - baths, toilets, shower screens etc will be installed
 - shelving installed
 - electrical completed
 - floor tiling will be completed
 - house will be cleaned inside and out and the fence will then be removed


Also, after all the trouble we have had with the bricks, NOW we are told they are going to Nawkaw them. We mentioned Nawkaw a few months back and were told that no it would not happen.


Went past yesterday afternoon and the painters were in, so we had a quick squiz. Other than the painting, the balcony floor has had the concrete bed laid.

All bathroom tiling has been completed and we are now very happy with this. Looks pretty good - would have liked to have lined up the grout lines, but I guess this just doesn't happen in a project build.